      2018-08-27 : Initial target 2018-09-28 (4weeks)

      2018-09-28 : Updated target 2018-10-12 (6weeks)
      Work is more complex than originally planned, need to install 2 SDKs in parallel

      2018-10-11 : Updated target 2018-10-26 (8weeks)
      Still encountering build issues which is being discussed with the BUILD team.

      Update as of 2018-10-26: Updated target 2018-11-09 (10 weeks)
      There are 2 packages remaining to be installed and it is being discussed with the BUILD team.

      2018-11-09: updated target of 2018-11-23 (12 weeks)

      • Moving to EVG identified some brittleness in the legacy tests.
      • Might move Robert onto this so Vincent can do the retryable reads design?
      • Adding two more weeks optimistically.

      2018-11-20 : updated target 2018-12-07 (14weeks)
      Almost done but need nuget package to be built before C# can be in EVG.

      Show
      2018-08-27 : Initial target 2018-09-28 (4weeks) 2018-09-28 : Updated target 2018-10-12 (6weeks) Work is more complex than originally planned, need to install 2 SDKs in parallel 2018-10-11 : Updated target 2018-10-26 (8weeks) Still encountering build issues which is being discussed with the BUILD team. Update as of 2018-10-26: Updated target 2018-11-09 (10 weeks) There are 2 packages remaining to be installed and it is being discussed with the BUILD team. 2018-11-09: updated target of 2018-11-23 (12 weeks) Moving to EVG identified some brittleness in the legacy tests. Might move Robert onto this so Vincent can do the retryable reads design? Adding two more weeks optimistically. 2018-11-20 : updated target 2018-12-07 (14weeks) Almost done but need nuget package to be built before C# can be in EVG.

      Build issues to be addressed in the near future.

      Tickets in this epic are about improving how we build the driver. Particularly important are to update our dependencies and to consolidate building our two targets using a single solution.

            Assignee:
            robert@mongodb.com Robert Stam
            Reporter:
            robert@mongodb.com Robert Stam
            Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

              Created:
              Updated:
              Resolved:
              14 weeks, 4 days