Summary: Use and improve the astrolabe tool to develop a comprehensive test suite for atlas planned maintenance impact on drivers
Cost in Eng Weeks: 2 Original | 8 To Date | 8 Est Final
2021-04-30: Updated target end date to 2021-05-14
Moved to code review earlier this week. Adding two weeks to account for reviews and responding to comments
Decided not to pause on this like other teams did because we were far enough in the implementation where pausing did not make sense
2021-04-20: Maintaining target end date of 2021-04-30
Merged the PR for unified test runner support of Atlas testing. Moving onto changes in drivers-atlas-testing.
2021-04-06: Updated target end date to 2021-04-30
All the unified test runner work is now complete and the draft PR is up
Implementing the workload executor is next up
2021-03-23: Updated target end date to 2021-04-16
After taking another look at the spec, Isabella realized that this would require more changes to the unified test runner than she originally anticipated. Adding 4 weeks to account for the remaining work, code reviews etc.
Working on updating Astrolabe to use the unified test runner
2021-03-09: Setting initial target end date to 2021-03-19
Currently working on updating Astrolabe to use the unified test runner
Engineer(s): Isabella
Summary: Use and improve the astrolabe tool to develop a comprehensive test suite for atlas planned maintenance impact on drivers
Cost in Eng Weeks: 2 Original | 8 To Date | 8 Est Final
2021-04-30: Updated target end date to 2021-05-14
Moved to code review earlier this week. Adding two weeks to account for reviews and responding to comments
Decided not to pause on this like other teams did because we were far enough in the implementation where pausing did not make sense
2021-04-20: Maintaining target end date of 2021-04-30
Merged the PR for unified test runner support of Atlas testing. Moving onto changes in drivers-atlas-testing.
2021-04-06: Updated target end date to 2021-04-30
All the unified test runner work is now complete and the draft PR is up
Implementing the workload executor is next up
2021-03-23: Updated target end date to 2021-04-16
After taking another look at the spec, Isabella realized that this would require more changes to the unified test runner than she originally anticipated. Adding 4 weeks to account for the remaining work, code reviews etc.
Working on updating Astrolabe to use the unified test runner
2021-03-09: Setting initial target end date to 2021-03-19
Currently working on updating Astrolabe to use the unified test runner