Define the post-Q3 plan for modularisation

    • Type: Icon: Task Task
    • Resolution: Done
    • Priority: Icon: Major - P3 Major - P3
    • None
    • Affects Version/s: None
    • Component/s: Not Applicable
    • Storage Engines
    • 5
    • StorEng - 2024-10-29

      One of the Q3 goals is
      We'll use what we learn to make a plan for where we want to be in 12 months, and for where we need to be in 6 months to support Disaggregated Storage.
      which requires we first undertake the work in Q3 to build an understanding of scope and engineering costs.

      This ticket will be started towards the end of Q3 and updates the tech design to outline post-Q3 modularity plan.